- Drag cost computation is often used on projects in order to justify additional project resources.
- This allows such cost to be attributed to individual critical path activities through their respective drag amounts ( i . e ., the activity's drag cost ).
- This in turn can allow a project manager to justify those additional resources that will reduce the drag and drag cost of specific critical path activities where the cost of such resources would be less than the value generated by reduction in drag.
- If the cost of each unit of time in the diagram above is $ 10, 000, the drag cost of E would be $ 200, 000, B would be $ 150, 000, A would be $ 100, 000, and C and D $ 50, 000 each.
- For example, if the addition of $ 50, 000 worth of resources would reduce the duration of B to ten days, the project would take only 55 days, B's drag would be reduced to five days, and its drag cost would be reduced to $ 50, 000.
- It's difficult to find drag cost in a sentence. 用drag cost造句挺難的
- For example, if a project s expected ROI will be reduced by $ 5, 000 for every day of duration, then an activity that has critical path drag of ten days ( i . e ., is delaying project completion by ten days ) will have a drag cost of $ 50, 000.
- If the addition of a resource that costs $ 10, 000 would reduce the activity s drag to five days, the drag cost would be reduced by $ 25, 000 and the project s expected ROI would be increased by $ 15, 000 ( $ 25, 000 minus the additional $ 10, 000 of resource costs ).
- The main purpose of the VBS is to prioritize components and work by the value they are expected to add, and to ensure that the value of the project investment is not reduced by the inclusion of work which has a value-added that is less than its true cost, which is the sum of its resource costs and its drag cost.
- The intent was to create an improved transport technology : the long tube can be pulled by a lower powered vessel than the equivalent tanker, the cargo can be handed off at the destination very quickly, and incurs no drag cost when empty ( because it can easily be taken aboard ), as compared to the similar unladen to laden drag of the rigid-hulled tanker of equivalent capacity.
- This can often happen if the project's critical path changes so that different activities suddenly acquire critical path drag and drag cost : an optional activity that adds $ 10, 000 to the expected value of the project and has a budget of $ 5, 000 may make sense when it can be performed off the critical path but should probably be jettisoned if on the critical path if they now have a negative value-added due to a drag cost of more than $ 5, 000.
- This can often happen if the project's critical path changes so that different activities suddenly acquire critical path drag and drag cost : an optional activity that adds $ 10, 000 to the expected value of the project and has a budget of $ 5, 000 may make sense when it can be performed off the critical path but should probably be jettisoned if on the critical path if they now have a negative value-added due to a drag cost of more than $ 5, 000.